Problem

Marie does three equally time-consuming tasks in a row without taking breaks. She begins the first task at 1:00 PM and finishes the second task at 2:40 PM. When does she finish the third task?

$\textbf{(A) }\text{3:10 PM}\qquad\textbf{(B) }\text{3:30 PM}\qquad\textbf{(C) }\text{4:00 PM}\qquad\textbf{(D) }\text{4:10 PM}\qquad\textbf{(E) }\text{4:30 PM}$

Solution