1951 AHSME Problems/Problem 13

Revision as of 08:53, 29 April 2012 by 1=2 (talk | contribs) (Created page with "== Problem == <math> A</math> can do a piece of work in <math> 9</math> days. <math> B</math> is <math> 50\%</math> more efficient than <math> A</math>. The number of days it tak...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Problem

$A$ can do a piece of work in $9$ days. $B$ is $50\%$ more efficient than $A$. The number of days it takes $B$ to do the same piece of work is:

$\textbf{(A)}\ 13\frac {1}{2} \qquad\textbf{(B)}\ 4\frac {1}{2} \qquad\textbf{(C)}\ 6 \qquad\textbf{(D)}\ 3 \qquad\textbf{(E)}\ \text{none of these answers}$

Solution

This problem needs a solution. If you have a solution for it, please help us out by adding it.

See Also

1951 AHSC (ProblemsAnswer KeyResources)
Preceded by
Problem 12
Followed by
Problem 14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
All AHSME Problems and Solutions