2004 AIME II Problems/Problem 5

Revision as of 10:17, 19 July 2018 by Flyhawkeye (talk | contribs) (Added Solution 2)

Problem

In order to complete a large job, $1000$ workers were hired, just enough to complete the job on schedule. All the workers stayed on the job while the first quarter of the work was done, so the first quarter of the work was completed on schedule. Then $100$ workers were laid off, so the second quarter of the work was completed behind schedule. Then an additional $100$ workers were laid off, so the third quarter of the work was completed still further behind schedule. Given that all workers work at the same rate, what is the minimum number of additional workers, beyond the $800$ workers still on the job at the end of the third quarter, that must be hired after three-quarters of the work has been completed so that the entire project can be completed on schedule or before?

Solution

A train is traveling at $1000$ miles per hour and has one hour to reach its destination $1000$ miles away. After $15$ minutes and $250$ miles it slows to $900$ mph, and thus takes $\frac{250}{900}(60)=\frac{50}{3}$ minutes to travel the next $250$ miles. Then it slows to $800$ mph, so the next quarter takes $\frac{250}{800}(60)=\frac{150}{8}$. The train then has $60-15-\frac{50}{3}-\frac{150}{8}=230/24$ minutes left to travel 250 miles, and doing the arithmetic shows that during this last stretch it must travel more than $1565$ mph to make it on time. Therefore the company needs to add $1566-800 = \boxed{766}$ more workers.

Solution by rocketscience

Solution 2

Let each worker's speed be $w$, the entire time be $t$, and the total work be $1$.


From the initial problem statement, we have $1000w\cdot\frac{1}{4}t=\frac{1}{4}$.


We need to find the time the next quarter takes to complete the same amount of work, which is $\frac{1000}{900}\cdot\frac{1}{4}\cdot t=\frac{5}{18}t$.


Similarly, we find that the time the third quarter takes is $\frac{1000}{800}\cdot\frac{1}{4}\cdot t=\frac{5}{16}t$.


Finally, the time the last quarter takes is $t\left[1-\left(\frac{1}{4}+\frac{5}{18}+\frac{5}{16}\right)\right]=\frac{23}{144}t$.


We then let the number of workers needed be $x$, so we have the equation $\left(800+x\right)w\cdot\frac{23}{144}t=\frac{1}{4}$. Dividing by the first equation, we have

\[\frac{800+x}{1000}\cdot\frac{\frac{23}{144}}{\frac{1}{4}}=1\] \[\frac{800+x}{1000}\cdot\frac{23}{36}=1\] \[800+x=\frac{36000}{23}\] \[x=\frac{17600}{23}.\]

We can't have a part of a worker, so we take the ceiling of $x$, which we find to be $\boxed{766}$.

-flyhawkeye

See also

2004 AIME II (ProblemsAnswer KeyResources)
Preceded by
Problem 4
Followed by
Problem 6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
All AIME Problems and Solutions

The problems on this page are copyrighted by the Mathematical Association of America's American Mathematics Competitions. AMC logo.png